980 m² Blinding Pour – Malton

​Client: Peter Duffy Ltd

Contractor: BCL

Supplier: Breedon Group

Location: Malton (YO17 9PJ)

​Deploying laser screed technology and synchronized Breedon ready-mix deliveries, BCL placed 980 m² of concrete blinding in 4 hours 20 minutes (08:00–12:20). Averaging 226 m²/hr, the continuous pour secured tight tolerances and delivered the slab early for follow-on trades.